OpenLegislation

Schedule 4 Certificates

Original text. Later amendments are not shown.

The italicised letters in the forms of certificates in this Schedule indicate the information to be included as follows—

(a)

name of engineer;

(b)

address of engineer;

(c)

name of panel to which engineer is appointed;

(d)

name of undertakers;

(e)

name of reservoir;

(f)

situation of reservoir, with sufficient detail to identify it (including the National Grid Reference of the approximate centre of the reservoir);

(g)

level above Ordnance Datum to which water may be filled, excluding the allowance made for flood conditions;

(h)

level above Ordnance Datum to which water may be stored, excluding the allowance made for flood storage;

(i)

date of preliminary or interim certificate as appropriate;

(j)

conditions subject to which the reservoir may be filled with water or water may be stored up to the level specified;

(k)

date of report, certificate, direction, as appropriate;

(l)

date of completion of works;

(m)

period recommended in the report within which the next inspection should be made;

(n)

date of inspecting engineer’s report;

(o)

name of inspecting engineer;

(p)

name of referee;

(q)

address of referee;

(r)

date of referee’s decision;

(s)

name of person appointing referee;

(t)

volume of water that makes a reservoir a “large raised reservoir” under the Act;

(u)

the time by which the water level must be reduced.

In these forms of certificates, square brackets and the words within them are not to be included where they are inappropriate.