The italicised letters in the form of directions in this Schedule indicate the information to be included as follows—
(a) name of engineer;
(b) address of engineer;
(c) name of panel to which engineer is appointed;
(d) name of undertakers;
(e) name of reservoir;
(f) situation of reservoir, with sufficient detail to identify it (including the National Grid Reference of the approximate centre of the reservoir);
(g) level above Ordnance Datum to which water may be filled, excluding the allowance made for flood conditions;
(h) level above Ordnance Datum to which water may be stored, excluding the allowance made for flood storage;
(i) date of preliminary or interim certificate as appropriate;
(j) conditions subject to which the reservoir may be filled with water or water may be stored up to the level specified;
(k) date of report, certificate, direction as appropriate;
(l) date of completion of works;
(m) period recommended in the report within which the next inspection should be made;
(n) date of inspecting engineer’s report;
(o) name of inspecting engineer;
(p) name of referee;
(q) address of referee;
(r) date of referee’s decision;
(s) name of person appointing referee;
(t) volume of water that makes a reservoir a large raised reservoir under the 1975 Act.
In these forms of directions, square brackets and the words within them are not to be included where they are inappropriate.

---
Source: https://www.legislation.gov.uk/wsi/2016/80/schedule/6 (the official version)
Page: https://openlegislation.uk/reservoirs-act-1975-capacity-registration-prescribed-forms-etc-wales-regulations-2016/schedule-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.