# Reservoirs (Scotland) Act 2011, Section 40: Preliminary and final certificates: compliance


The reservoir manager of a controlled reservoir must (subject to section 60(3)) comply with the requirements of any preliminary certificate or final certificate for the time being applicable to the reservoir.

---