# The Rivenhall Generating Station Extension (Correction) Order 2025, Article 2: Corrections


In relation to each of the provisions of the Rivenhall Generating Station Extension Order 2024 specified in the first column of the table in the Schedule, the erroneous text identified in the second column of each row is corrected in accordance with instructions in the third column.

---
Source: https://www.legislation.gov.uk/uksi/2025/533/article/2 (the official version)
Page: https://openlegislation.uk/rivenhall-generating-station-extension-correction-order-2025/article-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.