  "url": "https://openlegislation.uk/rivenhall-generating-station-extension-order-2024/article-9",
  "json_url": "https://openlegislation.uk/rivenhall-generating-station-extension-order-2024/article-9.json",
  "legislation": "uksi/2024/1391",
  "legislation_title": "The Rivenhall Generating Station Extension Order 2024",
  "legislation_url": "https://openlegislation.uk/rivenhall-generating-station-extension-order-2024",
  "path": "article/9",
  "kind": "article",
  "number": "9",
  "heading": "Certification of plans, etc.",
  "text": "(1) The undertaker must, as soon as practicable after the date on which this Order is made, submit to the Secretary of State copies of—\n(a) works plan;\n(b) Environmental Statement;\n(c) Existing Generation Station Plan;\n(d) Illustrative Plan; and\n(e) TCPA permission\nfor certification that they are true copies of the documents referred to in this Order.\n(2) A plan or document so certified is admissible in any proceedings as evidence of the contents of the document of which it is a copy.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Art. 9 in force at 20.12.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/1391/article/9",
    "retrieved_at": "2026-10-28T21:22:02.865055+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}