# The Rivenhall Generating Station Extension Order 2024, Article 9: Certification of plans, etc.

Extent: E+W

(1) The undertaker must, as soon as practicable after the date on which this Order is made, submit to the Secretary of State copies of—
(a) works plan;
(b) Environmental Statement;
(c) Existing Generation Station Plan;
(d) Illustrative Plan; and
(e) TCPA permission
for certification that they are true copies of the documents referred to in this Order.