# The River Humber Gas Pipeline Replacement Order 2016, Article 15: Access to works

Extent: E+W+S

(1) The undertaker may, for the purposes of the construction and/or the maintenance of the authorised project—
(a) form and lay out means of access, or improve existing means of access, as specified in column (2) of Schedule 7 (access to works); and
(b) with the approval of the relevant planning authority, which is not to be unreasonably withheld or delayed, after consultation with the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised project.

---