# The River Humber Gas Pipeline Replacement Order 2016, Paragraph 9: Co-operation

Extent: E+W+S

Where in consequence of the proposed construction of any of the authorised project, the undertaker requires the removal of apparatus under sub-paragraph 5(2)) or a statutory undertaker makes requirements for the protection or alteration of apparatus under paragraph 6(2), the undertaker must use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised project; and each statutory undertaker must use its reasonable endeavours to co-operate with the undertaker for that purpose.

---
Source: https://www.legislation.gov.uk/uksi/2016/853/schedule/10/part/1/paragraph/9 (the official version)
Page: https://openlegislation.uk/river-humber-gas-pipeline-replacement-order-2016/schedule-10/part-1/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.