# The River Humber Gas Pipeline Replacement Order 2016, Paragraph 12

Extent: E+W+S

Within the Order limits on the south bank of the estuary, from the crest of the flood defences to a point 750 metres landward (measured perpendicular to the flood defences) of the crest of the said defences, the pipeline shall be laid with a minimum cover of 1.7 metres above the pipeline.

---