  "url": "https://openlegislation.uk/river-humber-gas-pipeline-replacement-order-2016/schedule-10/part-3/paragraph-9",
  "json_url": "https://openlegislation.uk/river-humber-gas-pipeline-replacement-order-2016/schedule-10/part-3/paragraph-9.json",
  "legislation": "uksi/2016/853",
  "legislation_title": "The River Humber Gas Pipeline Replacement Order 2016",
  "legislation_url": "https://openlegislation.uk/river-humber-gas-pipeline-replacement-order-2016",
  "path": "schedule/10/part/3/paragraph/9",
  "kind": "paragraph",
  "number": "9",
  "heading": null,
  "text": "(1) The undertaker will not in the exercise of any powers conferred by this Order interfere with the Agency’s access to or maintenance of any drainage work unless a suitable alternative access is provided prior to and for the duration of any such interference.\n(2) The undertaker must not exercise the power conferred by articles 15 (access to works), 27 (temporary use of land for carrying out the authorised project) and 28 (temporary use of land for maintaining the authorised project) so as to interfere with any drainage work unless the exercise of such powers is with the consent of the Agency and in accordance with paragraphs 17 to 24 of this Part.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 10 Pt. 3 para. 9 in force at 15.9.2016, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2016/853/schedule/10/part/3/paragraph/9",
    "retrieved_at": "2026-10-28T23:20:42.702990+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}