# The River Humber Gas Pipeline Replacement Order 2016, Paragraph 12: Disputes

Extent: E+W+S

Any dispute arising between the undertaker and Centrica under this Part of this Schedule must be determined by arbitration as provided in article 46 (arbitration) unless otherwise agreed in writing between the undertaker and Centrica.

---
Source: https://www.legislation.gov.uk/uksi/2016/853/schedule/10/part/5/paragraph/12 (the official version)
Page: https://openlegislation.uk/river-humber-gas-pipeline-replacement-order-2016/schedule-10/part-5/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.