# The River Humber (The Deep Tidal Stream Generator) Order 2011, Article 13: Power to operate and use works


Subject to article 15, the undertaker may operate and use the authorised works as a system for generating and transmitting electricity.

---
Source: https://www.legislation.gov.uk/uksi/2011/1829/article/13 (the official version)
Page: https://openlegislation.uk/river-humber-the-deep-tidal-stream-generator-order-2011/article-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.