The undertaker shall remove—

(a)

Work No. 1 (except that, in relation to the four piles, if it is not practicable for the undertaker to effect a full removal of these, it shall cut each of the piles to two metres below the bed level); and

(b)

Work No. 2,

no later than three years after the date on which this Order is made and shall, subject to the exception in paragraph (a), restore the sites of the works to their former condition, subject to natural change.