(1)

Before commencing the construction of a tidal work the undertaker shall furnish to A. B. Ports for its approval, which it shall not unreasonably withhold, plans of the work showing the general mode of construction; and such works—

(a)

shall not be constructed otherwise than in accordance with such plans as may be approved by A. B. Ports; and

(b)

shall be executed to the reasonable satisfaction of A. B. Ports.

(2)

When submitting plans to the Secretary of State pursuant to article 5 of this Order, the undertaker shall—

(a)

send a copy of those plans to A. B. Ports; and

(b)

on receipt of approval of plans or of any conditions or restrictions imposed by the Secretary of State, send a copy to A. B. Ports.

(3)

If A. B. Ports fails to express its disapproval of any plans within 56 days after they have been delivered to it under sub-paragraph (1), it shall be deemed to have approved them.