# The River Mersey (Mersey Gateway Bridge) Order 2011, Paragraph 18

Extent: E+W+S

(1) If any canal work is abandoned, and is in such a condition that it is, or is likely to become, a danger to or to interfere with navigation, MSCC may by notice in writing require the undertaker to take such reasonable steps as may be specified in the notice to remove the work and (to such extent as MSCC reasonably requires) to restore the site to its former condition.
(2) If any canal work is in such condition that it is, or is likely to become, a danger to or to interfere with navigation, MSCC may by notice in writing require the undertaker to take such reasonable steps as may be specified in the notice—
(a) to repair and restore the work or part of it; or
(b) if the undertaker so elects, to remove the work and (to such extent as MSCC reasonably requires) to restore the site to its former condition.
(3) If—
(a) a work which consists of a canal work and a non-canal work is abandoned or falls into decay; and
(b) the non-canal work is in such a condition as to interfere with the right of navigation in the Canals or as to interfere with the rights of access or use of land adjacent to the Canals,
MSCC may include the non-canal work, or any part of it, in any notice under this paragraph.
(4) If after such reasonable period as may be specified in a notice under this paragraph the undertaker has failed to begin taking steps to comply with the requirements of the notice or after beginning has failed to make reasonably expeditious progress towards their implementation, MSCC may carry out the works specified in the notice and any costs incurred by MSCC in so doing shall be recoverable from the undertaker.
(5) In this paragraph “canal work” means so much of any specified work or any other work of which the undertaker is in possession under the powers conferred by this Order as is in or over the Canals and “non-canal work” means so much of any such work as is not in or over the Canals.

---
Source: https://www.legislation.gov.uk/uksi/2011/41/schedule/10/paragraph/18 (the official version)
Page: https://openlegislation.uk/river-mersey-mersey-gateway-bridge-order-2011/schedule-10/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.