# The River Mersey (Mersey Gateway Bridge) Order 2011, Paragraph 35

Extent: E+W+S

Before commencing the construction of a specified work the undertaker shall procure at its own expense, in liaison with and to the reasonable satisfaction of the Agency, a survey of any drainage work liable to be affected by the specified work.

---
Source: https://www.legislation.gov.uk/uksi/2011/41/schedule/10/paragraph/35 (the official version)
Page: https://openlegislation.uk/river-mersey-mersey-gateway-bridge-order-2011/schedule-10/paragraph-35
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.