# The River Tyne (Tunnels) Order 2005, Paragraph 35

Extent: E+W

In the event it is established that any accumulation or erosion mentioned in paragraph 32 or 33 would have been caused in any event by factors other than the construction of a tidal work, the undertaker shall be liable to remedy such accumulation or erosion only to the extent that the same is attributable to such construction as aforesaid.

---
Source: https://www.legislation.gov.uk/uksi/2005/2222/schedule/10/paragraph/35 (the official version)