  "url": "https://openlegislation.uk/river-tyne-tunnels-order-2005/schedule-10/paragraph-59",
  "json_url": "https://openlegislation.uk/river-tyne-tunnels-order-2005/schedule-10/paragraph-59.json",
  "legislation": "uksi/2005/2222",
  "legislation_title": "The River Tyne (Tunnels) Order 2005",
  "legislation_url": "https://openlegislation.uk/river-tyne-tunnels-order-2005",
  "path": "schedule/10/paragraph/59",
  "kind": "paragraph",
  "number": "59",
  "heading": null,
  "text": "In the assessment of any sums payable to Nexus under this Part of this Schedule there shall not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Nexus if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Part of this Schedule or increasing the sums so payable.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 10 para. 59 in force at 26.8.2005, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2005/2222/schedule/10/paragraph/59",
    "retrieved_at": "2026-10-29T04:54:14.602868+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}