Work No. 5 — Works to construct or install supporting buildings and facilities, including—
(a) diesel storage tanks;
(b) a process effluent storage tank;
(c) a demineralised water treatment plant;
(d) fire water tank, pump room(s) and fire protection facilities;
(e) a control room;
(f) administration block(s);
(g) a fully integrated distributed control system;
(h) workshop(s) and associated stores;
(i) spare parts storage facilities;
(j) security gatehouses and barriers;
(k) weighbridges;
(l) a heavy goods vehicle holding area;
(m) an external fuel container storage area;
(n) emergency stand-by generator(s);
(o) infrastructure for the transmission and/or storage of compressed natural gas;
(p) an outage contractor compound; and
(q) a permanent contractor laydown area.

---
Source: https://www.legislation.gov.uk/uksi/2020/419/schedule/1/paragraph/wrapper7n1 (the official version)
Page: https://openlegislation.uk/riverside-energy-park-order-2020/schedule-1/paragraph-wrapper7n1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.