# The Riverside Energy Park Order 2020, Paragraph 118: Arbitration

Extent: E+W

Save for differences or disputes arising under sub-paragraphs 110(2), 110(4) and 111(1) and paragraph 109 any difference or dispute arising between the undertaker and SGN under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and SGN, be determined by arbitration in accordance with article 42 (procedures in relation to certain approvals etc.).

---
Source: https://www.legislation.gov.uk/uksi/2020/419/schedule/10/paragraph/118 (the official version)
Page: https://openlegislation.uk/riverside-energy-park-order-2020/schedule-10/paragraph-118
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.