  "url": "https://openlegislation.uk/riverside-energy-park-order-2020/schedule-2/paragraph-20",
  "json_url": "https://openlegislation.uk/riverside-energy-park-order-2020/schedule-2/paragraph-20.json",
  "legislation": "uksi/2020/419",
  "legislation_title": "The Riverside Energy Park Order 2020",
  "legislation_url": "https://openlegislation.uk/riverside-energy-park-order-2020",
  "path": "schedule/2/paragraph/20",
  "kind": "paragraph",
  "number": "20",
  "heading": "River wall",
  "text": "(1) No part of Work No. 1 may commence until a river wall condition survey on those parts of the river wall within the order limits has been submitted to and approved by the Environment Agency (in consultation with the relevant planning authority).\n(2) The river wall condition survey submitted pursuant to sub-paragraph (1) must, where appropriate, identify any remedial works required to bring the tidal flood defence up to a good standard considering a design life of 100 years.\n(3) The remedial works required to bring the defence up to a good standard identified pursuant to sub–paragraph (2) must be carried out within two years of the date that the condition survey is approved under sub–paragraph (1).",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 20 in force at 1.5.2020, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2020/419/schedule/2/paragraph/20",
    "retrieved_at": "2026-10-28T22:31:05.557847+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}