# The Riverside Energy Park Order 2020, Paragraph 26: Decommissioning

Extent: E+W

(1) Within 24 months of the permanent cessation of the operation of Work No. 1, details of a scheme for the restoration and aftercare of the land for Work Nos. 1. 2, 3, 4 and 5 must be submitted to and approved by the relevant planning authority. The scheme must include details of structures and buildings to be demolished or retained, details of the means of removal of materials following demolition, phasing of demolition and removal, details of restoration works and phasing thereof.
(2) The scheme as approved under sub-paragraph (1) must be implemented in accordance with the phasing set out therein.

---