# The Riverside Energy Park Order 2020, Paragraph 8: Highway access

Extent: E+W

(1) No part of Work Nos. 6, 8, 9 and 10 may commence until written details of the siting, design and layout of any new permanent or temporary means of access to a highway in that part, or any alteration to an existing means of access to a highway in that part has been submitted to and approved by the relevant planning authority (in consultation with the relevant highway authority).
(2) The highway accesses must be constructed or altered as approved under sub-paragraph (1).
(3) The undertaker must not exercise the power in article 14(1) (permanent stopping up of streets) unless and until a plan showing the layout for the termination of the street (as specified in columns (1) and (2) of Schedule 6) has been submitted to and approved by the relevant planning authority, such plan to show the replacement turning head to facilitate a forward side–turn manoeuvre in forward and reverse gears by vehicles.

---
Source: https://www.legislation.gov.uk/uksi/2020/419/schedule/2/paragraph/8 (the official version)
Page: https://openlegislation.uk/riverside-energy-park-order-2020/schedule-2/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.