# The Riverside Energy Park Order 2020, Schedule 9: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Extent: E+W

(1) Location
(2) Number of plot shown on land plans
(3) Purpose for which temporary possession may be taken
In the London Borough of Bexley
2/43, 2/44, 2/48, 2/49, 02/52, 03/05
Temporary use as laydown, construction compound, construction use and accesses for as described in Work No. 8
In the Borough of Dartford
13/12
Temporary use as laydown, construction compound and construction use as described in Work No. 9c

---
Source: https://www.legislation.gov.uk/uksi/2020/419/schedule/9 (the official version)
Page: https://openlegislation.uk/riverside-energy-park-order-2020/schedule-9