Regulation 7 Notice of starting date of works
Subject to the proviso in regulation 5(1) and to paragraphs (2) and (4), for the purposes of section 114, an undertaker proposing to execute road works in a traffic-sensitive road shall, for each of the categories of work specified in column (1) of the table below, give a period of notice in relation to that category not less than that shown in column (2) of the table.
TABLE
| Category of works | Notice period |
|---|---|
| (1) | (2) |
| Urgent works | 2 hours. |
| Minor works not involving breaking up the road and the replacement of poles, lamps, columns and signs, pole testing and similar works involving minimal breaking up the road. | 3 days. |
| Standard works. | 7 days. |
| Minor works involving breaking up the road. | 7 days. |
| Remedial works by an undertaker to a reinstatement not causing danger to users of the road. | 3 days. |
Subject to the proviso in regulation 5(1), in a case where urgent works to which this paragraph applies are to be carried out in a traffic-sensitive road, which are works of a kind of which notice is required under section 114, the undertaker shall give notice as soon as reasonably practicable, and in any event within 2 hours of beginning the works. This paragraph applies to works—
for the purpose of restoring a supply or service where the supply or service is to premises to which it has been agreed in advance between the undertaker and the road works authority that this paragraph applies, and
where, without knowing, or having reasonable grounds for believing in the existence of circumstances justifying the execution of emergency works, the undertaker fears that, in the circumstances, persons or property might be endangered unless the works are carried out immediately,
and to such other works as cannot reasonably be severed from such works.
Subject to the proviso in regulation 5(1) and paragraph (4), for the purposes of section 114, an undertaker proposing to execute road works in a road which is not a traffic-sensitive road shall, for each of the categories of work specified in column (1) of the table below, give a period of notice in relation to that category not less than that shown in column (2) of the table.
TABLE
| Category of works | Notice period |
|---|---|
| (1) | (2) |
| Standard works. | 7 days. |
| Urgent works. | As soon as reasonably practicable and in any event within 2 hours of the works being begun. |
-
Provided, however, that in relation to roads to which this paragraph applies no notice is required in the case of minor works or remedial works by an undertaker to a reinstatement not causing danger to users of the road.
No notice pursuant to section 114 is required to be given by a statutory undertaker to any person to whom this paragraph applies, unless such a person has requested such a notice;
This paragraph applies—
to any statutory undertaker having apparatus in a road which is likely to be affected by the works; and
to any person who would otherwise be entitled to such notice solely by virtue of his having in the road part of a service pipe lying between the boundary of the road and the stopcock on such pipe in that road, or his having a drain in that road;
In this paragraph “drain”, “service pipe” and “stopcock” have the same meaning as in the Water Industry Act 1991f1.
For the purposes of section 114(7) the period at the end of which a notice shall cease to have effect in relation to any road works shall be the same as the period of notice specified for that category of works in the appropriate table in paragraph (1) or paragraph (3) as the case may be.