(1) No incineration of waste in Work No. 1 may take place, apart from during commissioning, until a grid connection comprised in Works No. 6A, 6B, 6C, 6D, 6E, 6F, 6G and 6H has been installed and is capable of transmitting electricity generated by Work No. 1.
(2) No waste may then be incinerated in Work No. 1 unless electricity is being generated by Work No. 1 except during periods of maintenance, inspection or repair or at the direction of the holder of a licence under section 6(1)(b) or (c) of the Electricity Act 1989 who is entitled to give such direction in relation to transmission of electricity from Work No. 1 to the national grid.

---
Source: https://www.legislation.gov.uk/uksi/2013/680/schedule/1/paragraph/36 (the official version)
Page: https://openlegislation.uk/rookery-south-resource-recovery-facility-order-2011/schedule-1/paragraph-36
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.