# The Rookery South (Resource Recovery Facility) Order 2011, Paragraph 7

Extent: E+W+S

The undertaker shall—
(a) at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
(b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.

---
Source: https://www.legislation.gov.uk/uksi/2013/680/schedule/7/paragraph/7 (the official version)