# The Scarweather Sands Offshore Wind Farm Order 2004, Paragraph 7


The undertaker must—
(a) at all times afford reasonable facilities to the engineer for access to any relevant work during its construction; and
(b) supply the engineer with all such information as the engineer may reasonably require with regard to any relevant work or the method of constructing it.

---
Source: https://www.legislation.gov.uk/wsi/2004/3054/schedule/6/paragraph/7 (the official version)
Page: https://openlegislation.uk/scarweather-sands-offshore-wind-farm-order-2004/schedule-6/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.