(1) The adjudicator may on his own initiative or on the application of a party correct his decision so as to remove a clerical or typographical error arising by accident or omission.
(2) Any correction of a decision must be made within five days of the delivery of the decision to the parties.
(3) As soon as possible after correcting a decision in accordance with this paragraph, the adjudicator must deliver a copy of the corrected decision to each of the parties to the contract.
(4) Any correction of a decision forms part of the decision.

---