# The Scheme for Construction Contracts in Northern Ireland Regulations (Northern Ireland) 1999, Paragraph 26: Effects of the decision

Extent: N.I.
Status: prospective

The adjudicator shall not be liable for anything done or omitted in the discharge or purported discharge of his functions as adjudicator unless the act or omission is in bad faith, and any employee or agent of the adjudicator shall be similarly protected from liability.

---
Source: https://www.legislation.gov.uk/nisr/1999/32/schedule/paragraph/26 (the official version)
Page: https://openlegislation.uk/scheme-for-construction-contracts-in-northern-ireland-regulations-northern-ireland-1999/schedule/paragraph-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.