# The Scheme for Construction Contracts in Northern Ireland Regulations (Northern Ireland) 1999, Paragraph 9: Notice of Intention to seek Adjudication

Extent: N.I.
Status: prospective

(1) An adjudicator may resign at any time on giving notice in writing to the parties to the dispute.
(2) An adjudicator must resign where the dispute is the same or substantially the same as one which has previously been referred to adjudication, and a decision has been taken in that adjudication.
(3) Where an adjudicator ceases to act under sub-paragraph (1)–
(a) the referring party may serve a fresh notice under paragraph 1 and shall request an adjudicator to act in accordance with paragraphs 2 to 7; and
(b) if requested by the new adjudicator and insofar as it is reasonably practicable, the parties shall supply him with copies of all documents which they had made available to the previous adjudicator.
(4) Where an adjudicator resigns in the circumstances referred to in sub-paragraph (2), or where a dispute varies significantly from the dispute referred to him in the referral notice and for that reason he is not competent to decide it, the adjudicator shall be entitled to the payment of such reasonable amount as he may determine by way of fees and expenses reasonably incurred by him. The parties shall be jointly and severally liable for any sum which remains outstanding following the making of any determination on how the payment shall be apportioned.

---
Source: https://www.legislation.gov.uk/nisr/1999/32/schedule/part/I/paragraph/9 (the official version)
Page: https://openlegislation.uk/scheme-for-construction-contracts-in-northern-ireland-regulations-northern-ireland-1999/schedule/part-I/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.