# The Scheme for Construction Contracts in Northern Ireland Regulations (Northern Ireland) 1999, Paragraph 10: Notice of intention to withhold payment

Extent: N.I.
Status: prospective

Any notice of intention to withhold payment mentioned in Article 10 of the 1997 Order shall be given not later than 7 days before the final date for payment determined either in accordance with the construction contract, or where no such provision is made in the contract, in accordance with paragraph 8.

---
Source: https://www.legislation.gov.uk/nisr/1999/32/schedule/part/II/paragraph/10 (the official version)
Page: https://openlegislation.uk/scheme-for-construction-contracts-in-northern-ireland-regulations-northern-ireland-1999/schedule/part-II/paragraph-10