# The Scheme for Construction Contracts in Northern Ireland Regulations (Northern Ireland) 1999, Paragraph 4: Dates for payment

Extent: N.I.
Status: prospective

Any payment of a kind mentioned in paragraph 2 shall become due on whichever of the following dates occurs later–
(a) the expiry of 7 days following the relevant period mentioned in paragraph 2(1); or
(b) the making of a claim by the payee.

---
Source: https://www.legislation.gov.uk/nisr/1999/32/schedule/part/II/paragraph/4 (the official version)
Page: https://openlegislation.uk/scheme-for-construction-contracts-in-northern-ireland-regulations-northern-ireland-1999/schedule/part-II/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.