# The Scheme for Construction Contracts in Northern Ireland Regulations (Northern Ireland) 1999, Paragraph 6: Dates for payment

Extent: N.I.
Status: prospective

Payment of the contract price under a construction contract (not being a relevant construction contract) shall become due on–
(a) the expiry of 30 days following the completion of the work; or
(b) the making of a claim by the payee,
whichever is the later

---
Source: https://www.legislation.gov.uk/nisr/1999/32/schedule/part/II/paragraph/6 (the official version)
Page: https://openlegislation.uk/scheme-for-construction-contracts-in-northern-ireland-regulations-northern-ireland-1999/schedule/part-II/paragraph-6