# The Scheme for Construction Contracts (Scotland) Regulations 1998, Paragraph 3: Dates for payment


Where the parties to a construction contract fail to provide an adequate mechanism for determining either what payments become due under the contract, or when they become due for payment, or both, the relevant provisions of paragraphs 4 to 7 shall apply.

---