Regulation 11 Transitional provision
In a case where a tenant applies to his landlord before 1st April 1996 for a qualifying repair to be carried out and, on the date the tenant applies, there is in force a contract between the landlord and a contractor—
which provides for the qualifying repair to be carried out by the contractor within a period which is longer than the first prescribed period, and
which was entered into before 1st April 1994, or
which was entered into on or after 1st April 1994 as a result of accepting an offer on the part of the contractor which was made in response to an invitation to submit such an offer and the invitation was given before 1st April 1994, the period provided for in the contract shall be substituted for the period specified in relation to the repair in column 2 of the Schedule.