Regulation 6 Substitute Contractor
Subject to paragraph (3) and regulation 8, if—
the qualifying repair has not been carried out within the first prescribed period, and
the tenant notifies the landlord that he requires another contractor to carry out the qualifying repair,
the landlord, where it is reasonably practicable, shall issue a further repair notice to another contractor and give a copy of the notice to the tenant.
The further repair notice shall contain a reference sufficient to identify it and specify the matters referred to in regulation 5(2)(a) to (e) and the last day of the second prescribed period.
Paragraph (1) does not apply if compliance with that paragraph would infringe the terms of a guarantee for work done or materials supplied of which the landlord has the benefit.