# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm (Amendment) Order 2025, Article 3: Amendments to Article 2 (Interpretation)


In article 2—
(a) after the definition of “access to works plan” insert—
““air gap” means the distance between the lowest point of the rotating blade of a wind turbine generator and HAT;” and
(b) in the definition of “outline operational drainage strategy (onshore substation)” omit “(onshore substation)” in both places that it occurs.

---
Source: https://www.legislation.gov.uk/uksi/2025/145/article/3 (the official version)
Page: https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-amendment-order-2025/article-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.