In Table 1 of Schedule 18 after the row for “Document number 6.3.28.2 (Environmental Statement Appendix 28.2 - Health Baseline Statistics)”—
(a) in column 1, insert “6.5”;
(b) in column 2, insert “REP8-021”;
(c) in column 3, insert “Schedule of Mitigation and Mitigation Route Map”;
(d) in column 4, insert “B”; and
(e) in column 5, insert “July 2023”.

---