(1) Subject to the provisions of this Order including the requirements—
(a) SEL is granted development consent for the Sheringham Shoal Extension Project and related ancillary works;
(b) DEL is granted development consent for the Dudgeon Extension Project and related ancillary works; and
(c) SEL and DEL are granted development consent for the integrated works;
to be carried out within the Order limits.
(2) Unless otherwise stated in Schedule 2, the requirements apply to scenario 1, scenario 2, scenario 3 and scenario 4.

---