# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Article 43: Procedure in relation to approvals, etc. under requirements

Extent: E+W

(1) Where an application is made to the relevant planning authority for any consent, agreement or approval required by a requirement, the following provisions apply in respect of that application as they would if the consent, agreement or approval so required were required by a condition imposed on a grant of planning permission—
(a) sections 78 (right to appeal against planning decisions and failure to take such decisions) and 79 (determination of appeals) of the 1990 Act;
(b) any orders, rules or regulations that make provision in relation to a consent, agreement or approval of a local planning authority required by a condition imposed on a grant of planning permission.
(2) For the purposes of paragraph (1), orders, rules and regulations make provision in relation to a consent, agreement or approval of a local planning authority required by a condition imposed on a grant of planning permission in so far as they make provision in relation to—
(a) an application for such a consent, agreement or approval;
(b) the grant or refusal of such an application; or
(c) a failure to give notice of a decision on such an application.
(3) Nothing in paragraph ‎(1)(b) affects the application of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017.

---
Source: https://www.legislation.gov.uk/uksi/2024/564/article/43 (the official version)
Page: https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/article-43/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.