# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Article 44: Modification of DOW section 36 consent

Extent: E+W

Upon commencement by the undertaker of any Work Nos. 1B, 2B, 3B or 3C, 4B or 4C, 5B or 5C the provisions of the DOW section 36 consent shall be amended as follows—
(a) In condition 3, for “560MW” substitute “402MW”; and
(b) In Annex B, under the heading “Maximum Number of Turbines” for “77” substitute “67”.

---