# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Paragraph 3

Extent: E+W

Cables and cable crossings
(1) Within Work No. 2A, the in-field cables must not, in total—
(a) exceed 36 in number;
(b) exceed 90 kilometres in length;
(c) exceed 0 cable crossings;
(d) have cable protection (including cable crossings) exceeding 4,000 square metres in area; or
(e) have cable protection (including cable crossings) exceeding 1,000 cubic metres in volume.

---