# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Paragraph 24: Seasonal Restriction

Extent: E+W

(1) The undertaker must not carry out any cable installation works within the GW during the winter period.
(2) For the purpose of this condition—
“the GW” means the site designated as the Greater Wash Special Protection Area;
“winter period” means the period between 1 November to 31 March inclusive.

---
Source: https://www.legislation.gov.uk/uksi/2024/564/schedule/13/paragraph/24 (the official version)
Page: https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-13/paragraph-24
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.