# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Paragraph 22

Extent: E+W

In relation to any dispute arising under this part of this Part of this Schedule (except for those disputes referred to in paragraph 11) the provisions of article 42 (arbitration) shall not apply and any such dispute, unless otherwise provided for, must be referred to and settle by a single arbitrator to be agreed between the parties, or failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) to the President of the Institute of Civil Engineers.

---
Source: https://www.legislation.gov.uk/uksi/2024/564/schedule/14/paragraph/22 (the official version)
Page: https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-14/paragraph-22
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.