# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Paragraph 24

Extent: E+W

The offshore works may not be commenced until a plan for the work of the GCSG has been submitted to and approved by the Secretary of State following consultation with the members of the GCSG. Such plan must include—
(a) terms of reference for the GCSG;
(b) details of the membership of the GCSG;
(c) details of the schedule of meetings, timetable for preparation of the Guillemot CIMP and reporting and review periods; and
(d) the dispute resolution mechanism.

---
Source: https://www.legislation.gov.uk/uksi/2024/564/schedule/17/paragraph/24 (the official version)