{
  "url": "https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-2/part-1/paragraph-15",
  "json_url": "https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-2/part-1/paragraph-15.json",
  "legislation": "uksi/2024/564",
  "legislation_title": "The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024",
  "legislation_url": "https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024",
  "path": "schedule/2/part/1/paragraph/15",
  "kind": "paragraph",
  "number": "15",
  "heading": "Traffic and Transport",
  "text": "(1) No phase of the onshore works may commence until for that phase a construction traffic management plan (which must be in accordance with the outline construction traffic management plan), as appropriate for the relevant phase, has for that phase been submitted to and approved by the relevant planning authority in consultation with Norfolk County Council or in respect of the strategic road network National Highways.\n(2) Any plan submitted under sub-paragraph ‎(1) may cover one or more phase of the onshore works.\n(3) Each plan approved under sub-paragraph ‎(1) must be implemented upon commencement of the relevant phase of the onshore works.\n(4) If any of the accesses identified in the outline construction traffic management plan are required for pre-commencement archaeological investigations, a specific plan for such accesses which must accord with the relevant details set out in the outline construction traffic management plan must be submitted to and approved by the relevant planning authority, in consultation with Norfolk County Council or in respect of the strategic road network National Highways, prior to the construction and use of such accesses. The accesses identified must be constructed and used in accordance with the details contained in the specific plan so approved.\n(5) During construction of the authorised development, the maximum daily vehicle trips set out in Annex A of the outline construction traffic management plan must not be exceeded.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 Pt. 1 para. 15 in force at 9.5.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/564/schedule/2/part/1/paragraph/15",
    "retrieved_at": "2026-10-28T21:30:20.840898+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}