# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Paragraph 17: Operational Drainage Strategy

Extent: E+W

(1) In the event of scenario 1 or scenario 2, each of Work Nos. 15A, 15B, 18A and 18B must not commence until a written plan for drainage during operation of the relevant work, has been submitted to and approved by the relevant planning authority, following consultation with the lead local flood authority and the Environment Agency.
(2) In the event of scenario 3 or scenario 4, Work No. 15C, 18A and 18B must not commence until a written plan for drainage during operation of the relevant work, has been submitted to and approved by the relevant planning authority, following consultation with, the lead local flood authority and the Environment Agency.
(3) Each operational drainage strategy must accord with the principles for the relevant work set out in the outline operational drainage strategy ..., must include a timetable for implementation, and must include provision for the maintenance of any measures identified.
(4) Each operational drainage strategy must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2024/564/schedule/2/part/1/paragraph/17 (the official version)
Page: https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-2/part-1/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.