# The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024, Paragraph 19: Code of construction practice

Extent: E+W

(1) No phase of the onshore works may commence until a code of construction practice (which must accord with the outline code of construction practice) for that phase has been submitted to and approved by the relevant planning authority following consultation as appropriate with Norfolk County Council, the Environment Agency, Natural England and, if applicable, the MMO.
(2) Any code of construction practice submitted under sub-paragraph ‎(1) may cover one or more phase of the onshore works.
(3) All construction works for each phase must be undertaken in accordance with the relevant approved code of construction practice.
(4) Pre-commencement screening and fencing works must only take place in accordance with a specific plan for such pre-commencement works which must accord with the relevant details for screening and fencing security set out in the outline code of construction practice, and which has been submitted to and approved by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2024/564/schedule/2/part/1/paragraph/19 (the official version)
Page: https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-2/part-1/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.