{
  "url": "https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-2/part-1/paragraph-30",
  "json_url": "https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024/schedule-2/part-1/paragraph-30.json",
  "legislation": "uksi/2024/564",
  "legislation_title": "The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024",
  "legislation_url": "https://openlegislation.uk/sheringham-shoal-and-dudgeon-extensions-offshore-wind-farm-order-2024",
  "path": "schedule/2/part/1/paragraph/30",
  "kind": "paragraph",
  "number": "30",
  "heading": "Notification of generation of power",
  "text": "(1) SEL must notify the relevant planning authority and the MMO upon first generation of power from each phase of the Sheringham Shoal Extension Project no later than seven days after the occurrence of this event.\n(2) DEL must notify the relevant planning authority and the MMO upon first generation of power from each phase of the Dudgeon Extension Project no later than seven days after the occurrence of this event.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 Pt. 1 para. 30 in force at 9.5.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/564/schedule/2/part/1/paragraph/30",
    "retrieved_at": "2026-10-28T21:30:20.840898+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}